●During project execution, the customer authorizes and funds a scope change which requires

● During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule: A Now becomes the new schedule, including the changes, and the original baseline is disregarded. B Is still the original baseline but annotated to reflect that a change has taken place. C Is amended to reflect the scope change, but the original baseline is still maintained for post-project review. D Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.) E Is the same since baseline schedules cannot change once the development phase is completed.